Online Homework help| Sample solutions about the mojo project

  1. WORKSHEET
Task Optimistic (O) Likely (L) Pessimistic (P) EXPECTED TASK E=O+4L+P/6 (DAYS)
A 2 6 9 6
B 18 19 20 19
C 10 12 14 12
D 12 18 24 18
E 13 14 16 14
F 8 12 16 12
G 6 8 10 8
H 17 20 21 20

 

 

 

 

 

 

 

 

2.     

 

 

PATH

(Listing of tasks on the path)

EXPECTED PATH LENGTH (DAYS)
ABFH 6+19+12+20=57

(CRITICAL PATH)

ACFH 6+12+12+20=50
ADFH 6+18+12+20=56
ADGH 6+18+8+20=52
EGH 14+8+20=42
   

 

 

 
4. A, D, I, L, M

5. 31 WEEKS

6. Tasks L and M. This is to save 2weeks from crush L to finish in 8weeks and 2weeks from crush M to finish in 6weeks and the project to finish in the expected time of 31 weeks.

7. $6,000 is the total additional cost of the crush.